Our first production unit for the Upgrade Project; PAF #33; is undergoing functional testing at the EMC chamber following removal of PAF #32. Stability testing using the linear power regulators inside the EMC chamber will firstly be conducted followed by temperature ramp testing. We expect to have the balance of dominos for the remaining PAFs in hand by the end of May. Full requirements of power bulkheads are going through surface mount and hand assembly and may be ready for pick up next week. This will leave only the PAF controllers to be able to complete the electronic assembly of all PAFs.

Currently there are an additional three front-end control modules in working order and the plan is to ship a set of three completed PAFs for installation some time around September this year.